Building permits in Costa Rica: who does what
A building permit is not issued by a single office. Several institutions are involved, each reviews a different part of the project, and the order of the procedures changes how long everything takes. This is the general route we follow with our clients, and what falls to each party.

Before the drawings: the lot must allow the project
Everything starts with what is checked before buying or designing: land use, setbacks, access and water availability. If you do not have the lot yet, first read what to check before buying a lot. If you already own it, those documents are the first ones requested.
1. The responsible professional and CFIA
The construction drawings are signed by an architect or engineer registered with the Federated College of Engineers and Architects (CFIA). The project is registered on the APC system, the platform where CFIA, INVU and the Ministry of Health take part, with the professional services contract between you and the professional. Each of them reviews its own part. The College's fees are paid here as well.
2. Land use and road alignments
The municipality confirms that the project's use is allowed in the zone. If the lot fronts a national road, the Ministry of Public Works (MOPT) defines the alignment and the setback from the right-of-way. On local roads, the municipality defines it.
3. Water and wastewater
You need water availability from AyA, the local ASADA or the municipality, depending on the case. Where there is no sewer, the wastewater treatment design (usually a septic tank with a drain field, backed by a soil percolation test) is also submitted with the project.
4. Environmental viability
SETENA decides whether the project needs an environmental procedure, and of what kind, depending on its size, use and the area's environmental fragility. A small house usually follows a simple procedure, while a condominium or a hotel may require full studies. It is the procedure whose timing varies the most, which is why it is started early.
5. Fire department and Ministry of Health, when applicable
Depending on the project's use and size, the drawings are also submitted to the Fire Department to review fire protection and emergency exits. Commercial projects, hotels and multi-family buildings almost always go through it. The Ministry of Health takes part in treatment systems and, later, in the operating permit for businesses.
6. The municipality: the permit itself
With the other documents in order, the project is submitted to the municipality. It checks compliance with the zoning plan or the regulations that apply, charges the construction tax, which is a percentage of the value of the work, and issues the permit. The INS workers' compensation policy for the construction is also paid. Do not start building without the permit in hand.
7. During construction
The permit does not end the process. The work remains under a responsible professional, a site log is kept, and the municipality may inspect. When finished, the occupancy approval or final sign-off is processed, which is needed to connect permanent utilities and to register the building.
How long it takes
It depends on the municipality, the type of project and whether the documents arrive complete the first time. Most delays come from environmental viability and missing documents, not from the drawings. That is why it pays to process in parallel whatever can be, and to review the full file before submitting it.
What we do and what falls to you
- We do: the drawings and the project registration. If you hire the permits phase, we coordinate the process with an outside consultant before SETENA, APC, AyA, the Fire Department and the municipality, and follow up on the file.
- You do: provide the lot documents (survey plan and registry certificate) and the personal or company documents of the owner, pay the fees and taxes, and take out the workers' compensation policy.
This guide is general. Requirements, amounts and timelines vary by canton and institution and change over time, so they must always be confirmed with each one. It is not legal advice.